An earthing test link is a removable bolted link between the earth electrode and the rest of the earthing system. Opening it isolates that one electrode so its resistance can be measured on its own — without digging anything up. Without one, every pit reads as part of a single parallel network and a failing electrode hides behind its healthy neighbours.
This guide covers what a test link is, the types you will see, where it sits, how to test through it step by step, and the mistakes that make readings useless.
What is an earthing test link?
An earthing test link — also called a test joint or disconnecting link — is a short bolted strip, normally gunmetal, brass or GI, connecting the electrode terminal to the outgoing earth conductor. It sits inside the earth pit chamber, under the cover, so it can be reached in a minute. Unbolt it and the electrode is physically separated from the system. That separation is the entire purpose.
Test link types and materials compared
| Type | Typical material | Best for | Watch out for |
|---|---|---|---|
| Bolted link (single or double bolt) | Gunmetal / brass | Permanent earth pits, repeated testing | Needs a clean, tight face each time it is reclosed |
| Strip-type disconnecting link | Hot-dip galvanised steel | Cost-sensitive general earthing, GI strip systems | Zinc wears with repeated opening; inspect for rust |
| Copper test link | Copper | Copper-strip and coastal or corrosive sites | Match to copper conductor to avoid galvanic mismatch |
| Test point / inspection terminal | Brass or stainless fittings | Pits where a full link is not practical | Gives access for the tester but not full isolation — check what your design requires |
Whatever the material, the link carries fault current when closed, so it is sized with the earthing conductor — not chosen by appearance. Mixing metals at the joint (for example a bare steel link on a copper strip in a damp chamber) is how a joint quietly adds resistance over the years.
Why every earth pit needs one
- Isolation: measure one electrode, not the whole network.
- Fault finding: find the single pit that has drifted out of range.
- Compliance: IS 3043 practice expects an earthing system that can be inspected and tested; inspectors look for test points.
- Maintenance record: a dated reading per pit shows the trend, so you act before a failure rather than after.
Specify test links with your electrodes: Ashlok earthing accessories · Ashlok earthing electrodes
How to test earth resistance through a test link — step by step
- Check that the system is safe to work on and that the installation can tolerate the pit being disconnected for a few minutes. Never open a link during a thunderstorm.
- Lift the chamber cover and clean the link faces.
- Unbolt the link so the electrode is isolated from the earth conductor.
- Connect the tester to the electrode side. Drive the current and potential probes in a straight line away from the pit, well outside its zone of influence.
- Record the reading and repeat with the potential probe moved slightly each way — readings should agree. If they drift, move the probes further out. The full method is in how to check earthing resistance.
- Compare against the design target — see acceptable earth resistance values as per IS 3043; for lightning earths see lightning arrester earth pit resistance.
- Clean, re-bolt the link tightly and confirm continuity back to the earth bar before leaving.
Common mistakes that spoil a test
- Testing with the link closed — you measure the whole network, not the pit.
- Leaving the link loose after the test, which turns a good pit into a high-resistance joint.
- Probes too close to the pit or to each other, so their resistance areas overlap.
- Testing straight after heavy rain and assuming the number is typical.
- A buried or paved-over chamber with no access — the pit might as well not have a link.
How often should you test?
At commissioning, then periodically — commonly once a year and before the monsoon — and after any earth fault, lightning strike or civil work near the pit. Keep a simple log of date, reading, soil condition and instrument, so the trend is visible.
Frequently asked questions
What is an earthing test link used for? To isolate a single earth electrode so its resistance can be measured accurately, without being masked by other electrodes in the network.
What is the difference between a test link and an earth bar? The earth bar is the common bonding point for all conductors. The test link is the openable joint between one electrode and that system.
Where is the test link located? Inside the earth pit chamber at ground level, between the electrode terminal and the outgoing earth conductor.
Can I test earth resistance without a test link? A clamp-on tester can give a loop reading on a multi-electrode system, but it does not isolate a single pit. For a clean fall-of-potential measurement, a test link is the dependable method.
What material is best for a test link? Gunmetal or brass for permanent pits; copper where the system is copper and conditions are corrosive; galvanised steel where cost is the priority and the joint will be inspected.
Ashlok has manufactured earthing and lightning protection products since 1999. See earthing accessories → · Related: earth pit chamber cover guide and earthing accessories guide.